NSW Major Mining Project Development Assessment and Approval Process
Environmental investigations begin and concept mine plans developed (by proponent)
![]()
[Community consultation may begin (ongoing)]
![]()
Conceptual Project Development Plan meeting (DPI)
![]()
Planning Focus (Department of Planning (DoP))
![]()
Lodgement of Major Project Application with DoP
![]()
Environmental Assessment (EA) Requirements issued (DoP) (“Director-General’s requirements”)
![]()
EA Studies and Preparation of EA
![]()
Draft EA lodged for adequacy test (with key Govt. Agencies)
![]()
Public exhibition of EA and submissions invited (generally 30+ days)
![]()
Assessment of EA and submissions by DoP
![]()
Minister for Planning may appoint IHAP (Independent Hearing & Assessment Panel) to advise on certain key issues
![]()
Minister for Planning determines project application
![]()
(If project approved) Minister for Mineral Resources grants Mining Lease