The NSW Mineral Exploration and Development Assessment and Approvals Process for Major Mining Projects
Invitation from Minister for Mineral Resources to apply for a Coal Exploration Licence (EL)
![]()
EL Application (ELA) lodged, processed and determined.
![]()
Local Community advised of proposed grant of ELA
(Newspaper notification)
![]()
Grant of EL with environmental conditions and security bond
![]()
Exploration, Environmental and Feasibility investigations begins
![]()
[Community and landholder consultation commences (ongoing)]
(may possible involve the formation of a Community Consultative Committee)
![]()
Mineable resource defined and concept mine plans developed
![]()
Presentation of Conceptual Project Development Plan to I&I NSW- Minerals
![]()
On acceptance of mine concept, Department of Planning (DoP) notified.
![]()
Inter Agency Planning Focus Meeting (PFM) organised by DoP
![]()
Lodgement of Major Project Application with DoP
(Lodgement of Mining Lease Application (MLA with I&I NSW) #1
![]()
Environmental Assessment (EA) Requirements Issued
(Director-General’s Requirements)
![]()
EA Studies and Preparation of EA
![]()
Draft EA lodged for adequacy test (with key Govt. Agencies)
![]()
Public exhibition of EA and submissions invited (> 5 wks)
![]()
Assessment of EA and submissions by DoP
![]()
Minister for Planning may appoint PAC (Planning Advisory Committee) to advise on certain key issues
![]()
Minister for Planning determines application
![]()
Grant of Development Approval with conditions
![]()
Minister for Mineral Resources grants a Mining Lease (ML) #2
(with security and conditions)
![]()
Preparation and submission of Mining Operations Plan (MOP) to I&I NSW
(Condition of ML)
![]()
Security Bond reassessed from the MOP
(additional security lodged)
![]()
Approvals and Licences obtained form other NSW Government agencies
(Secured through the Part 3A process of the EP&A Act 1979)
![]()
Access Agreements/ Arrangements with Landowners
![]()
Commencement of Mining Operations
Notes:
#1 MLA may be lodged at any time (its processing undertaken in parallel with the approvals process).
#2 An ML can only be granted when there is a valid development approval (consent).